Dept. of Trans. PROGRESS Serial No. Contract No. 16-027-12-26 08-0Q7404 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 72% Location: Federal Project: 08-SBD-15-R15.4/30.8 IM-015-1(230) Progress payment No. 028 Payment period ending: 01-20-16 COFFMAN/PARSONS A JOINT VENTURE 9685 VIA EXCELENCIA SUITE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 103,611,866.20 1,441,752.10 2. a. Extra Work 1,766,749.87 0.00 b. Adustment Comp. -562,200.00 -112,440.00 3. Materials on Hand 121,430.83 0.00 4. Earned Subject to Retention 104,937,846.90 1,329,312.10 5. Mobilization 6. Total Work Completed 104,816,416.07 7. Deductions -342,270.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 104,595,576.90 1,339,312.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,339,312.10