Dept. of Trans. PROGRESS Serial No. Contract No. 15-266-08-51 08-0Q7514 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 52% Location: Federal Project: 08-SBD-60-R0.0/R4.6 NHP-P060(146) 08-RIV-60-R3.0/R6.9 Progress payment No. 005 Payment period ending: 09-16-15 CHUMO CONSTRUCTION INC. 14425 JOANBRIDGE STREET BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,506,453.84 467,940.67 2. a. Extra Work 154,819.10 23,914.43 b. Adustment Comp. 3. Materials on Hand 0.00 -23,396.22 4. Earned Subject to Retention 5,661,272.94 468,458.88 5. Mobilization 740,000.00 0.00 6. Total Work Completed 6,401,272.94 7. Deductions -2,776.96 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,398,495.98 468,458.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 468,458.88