Dept. of Trans. PROGRESS Serial No. Contract No. 22-024-13-28 08-0Q75U4 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 97% Location: Federal Project: 08-SBD-60-R4.6/R9.9 ACHS-NHP0-6(14) 08-RIV-60-R0.0/12.2 Progress payment No. 032 Payment period ending: 01-20-22 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 118,653,331.50 153,667.10 2. a. Extra Work 9,866,846.60 106,850.29 b. Adustment Comp. 1,644,847.28 0.00 3. Materials on Hand 4. Earned Subject to Retention 130,165,025.38 260,517.39 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 136,165,025.38 7. Deductions -17,625.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 136,147,400.38 267,517.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 267,517.39