Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 16-154-15-00 08-0Q7604 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 55% Location: Federal Project: 08-SBD-10-0.0/30.9 NHPI-010-2(262) Progress payment No. 015 Payment period ending: 05-19-16 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,634,256.20 443,555.65 2. a. Extra Work 497,131.54 0.00 b. Adustment Comp. 528,982.23 0.00 3. Materials on Hand 123,216.03 0.00 4. Earned Subject to Retention 23,783,586.00 443,555.65 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 25,660,369.97 7. Deductions -98,111.26 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,685,474.74 443,555.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 443,555.65