Dept. of Trans. PROGRESS Serial No. Contract No. 14-057-15-23 08-0Q8504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 56% 08-RIV-15-31.9/52.2 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-20-14 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 149,718.36 0.00 2.a. Extra Work 16,979.31 16,979.31 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 166,697.67 16,979.31 5. Mobilization 37,500.00 0.00 6. Total Work Completed 204,197.67 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 204,197.67 16,979.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,979.31