Dept. of Trans. PROGRESS Serial No. Contract No. 20-297-10-34 08-0Q9104 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 49% Location: Federal Project: 08-SBD-10-R23.8/R23.8 B1IM-010-2(267) Progress payment No. 014 Payment period ending: 10-20-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,469,523.60 1,258,183.90 2. a. Extra Work 324,292.85 108,898.19 b. Adustment Comp. 3. Materials on Hand 323,359.43 -134,365.97 4. Earned Subject to Retention 8,117,175.88 1,232,716.12 5. Mobilization 900,000.00 45,000.00 6. Total Work Completed 8,693,816.45 7. Deductions -20,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,997,175.88 1,287,716.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,287,716.12