Dept. of Trans. PROGRESS Serial No. Contract No. 20-358-07-06 08-0Q9104 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 49% Location: Federal Project: 08-SBD-10-R23.8/R23.8 B1IM-010-2(267) Progress payment No. 015 Payment period ending: 12-20-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,469,523.60 0.00 2. a. Extra Work 351,260.64 26,967.79 b. Adustment Comp. 3. Materials on Hand 323,357.00 -2.43 4. Earned Subject to Retention 8,144,141.24 26,965.36 5. Mobilization 900,000.00 0.00 6. Total Work Completed 8,720,784.24 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,034,141.24 36,965.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,965.36