Dept. of Trans. PROGRESS Serial No. Contract No. 21-172-09-37 08-0Q9104 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 70% Location: Federal Project: 08-SBD-10-R23.8/R23.8 B1IM-010-2(267) Progress payment No. 019 Payment period ending: 06-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,553,352.10 383,502.50 2. a. Extra Work 371,984.55 0.00 b. Adustment Comp. 3. Materials on Hand 325,530.43 -3,859.00 4. Earned Subject to Retention 9,250,867.08 379,643.50 5. Mobilization 900,000.00 0.00 6. Total Work Completed 9,825,336.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,150,867.08 379,643.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 379,643.50