Dept. of Trans. PROGRESS Serial No. Contract No. 21-235-11-15 08-0Q9104 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 93% Location: Federal Project: 08-SBD-10-R23.8/R23.8 B1IM-010-2(267) Progress payment No. 021 Payment period ending: 08-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,939,473.60 1,637,852.50 2. a. Extra Work 371,984.55 0.00 b. Adustment Comp. 3. Materials on Hand 94,309.38 -271,676.05 4. Earned Subject to Retention 11,405,767.53 1,366,176.45 5. Mobilization 900,000.00 0.00 6. Total Work Completed 12,211,458.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,305,767.53 1,366,176.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,366,176.45