Dept. of Trans. PROGRESS Serial No. Contract No. 22-081-13-59 08-0R1424 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 86% Location: Federal Project: 08-SBD-40-R125.0/R154.6 HSIM-040-2(66) Progress payment No. 012 Payment period ending: 03-20-22 AMES CONSTRUCTION INC 391 N MAIN ST #302 CORONA CA 92880 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,856,851.65 726,542.00 2. a. Extra Work 119,673.30 28,756.93 b. Adustment Comp. 137,500.00 25,000.00 3. Materials on Hand 4. Earned Subject to Retention 10,114,024.95 780,298.93 5. Mobilization 1,120,000.00 0.00 6. Total Work Completed 11,234,024.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,234,024.95 780,298.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 780,298.93