Dept. of Trans. PROGRESS Serial No. Contract No. 20-114-13-15 08-0R1604 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 95% Location: Federal Project: 08-SBD-40-R50.0/R75.0 HSIM-040-1(84) Progress payment No. 015 Payment period ending: 04-20-20 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,374,709.40 314,390.00 2. a. Extra Work 1,952,975.13 45,277.90 b. Adustment Comp. 16,124,015.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 28,451,699.53 359,667.90 5. Mobilization 3,387,465.00 0.00 6. Total Work Completed 31,839,164.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,839,164.53 359,667.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 359,667.90