Dept. of Trans. PROGRESS Serial No. Contract No. 17-172-16-13 08-0R4404 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 27% Location: Federal Project: 08-SBD-15-R23.0/R26.2 NHPI-151(240) Progress payment No. 003 Payment period ending: 06-20-17 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 238,714.49 185,380.97 2. a. Extra Work 20,952.06 20,952.06 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 259,666.55 206,333.03 5. Mobilization 73,217.45 34,681.95 6. Total Work Completed 332,884.00 7. Deductions 0.00 19,996.32 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 332,884.00 261,011.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 261,011.30