Dept. of Trans. PROGRESS Serial No. Contract No. 17-233-15-40 08-0R4404 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 60% Location: Federal Project: 08-SBD-15-R23.0/R26.2 NHPI-151(240) Progress payment No. 005 Payment period ending: 08-18-17 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 385,494.09 71,226.16 2. a. Extra Work 27,900.21 6,948.15 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 413,394.30 78,174.31 5. Mobilization 77,071.00 3,853.55 6. Total Work Completed 490,465.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 490,465.30 82,027.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,027.86