Dept. of Trans. PROGRESS Serial No. Contract No. 16-362-16-16 08-0R4504 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 69% Location: Federal Project: 08-SBD-15-R20.0/R23.0 NHP-015-1(241) Progress payment No. 003 Payment period ending: 12-20-16 A M CONCRETE INC 13170 TELFAIR AVE SYLMAR CA 91392 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 672,717.00 232,768.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 672,717.00 232,768.00 5. Mobilization 122,000.00 0.00 6. Total Work Completed 794,717.00 7. Deductions -38,017.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 756,699.50 232,768.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 232,768.00