Dept. of Trans. FINAL Serial No. Contract No. 18-149-12-17 08-0R4504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-15-R20.0/R23.0 NHP-015-1(241) Progress payment No. 006 Payment period ending: 01-20-17 A M CONCRETE INC 13170 TELFAIR AVE SYLMAR CA 91392 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 675,877.00 0.00 2. a. Extra Work 18,449.51 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 694,326.51 0.00 5. Mobilization 122,000.00 0.00 6. Total Work Completed 816,326.51 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 806,326.51 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00