Dept. of Trans. PROGRESS Serial No. Contract No. 16-266-10-48 08-0R4604 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 94% Location: Federal Project: 08-RIV-91-10.8/12.9 NHP-P091(141) Progress payment No. 009 Payment period ending: 09-20-16 YAKAR 689 EAST SAN BERNARDINO RD COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 854,687.12 219,743.55 2. a. Extra Work 185,811.24 133,769.36 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,040,498.36 353,512.91 5. Mobilization 45,000.00 0.00 6. Total Work Completed 1,085,498.36 7. Deductions -88,378.23 -87,378.23 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 997,120.13 266,134.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 266,134.68