Dept. of Trans. PROGRESS Serial No. Contract No. 17-025-13-58 08-0R5104 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 46% Location: Federal Project: 08-SBD-15-7.0/R20.0 STP-X071(67) STPH Progress payment No. 004 Payment period ending: 01-20-17 WESTCOAST PUBLIC WORK INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 615,588.70 321,527.70 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 615,588.70 321,527.70 5. Mobilization 80,000.00 4,000.00 6. Total Work Completed 695,588.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 695,588.70 325,527.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 325,527.70