Dept. of Trans. PROGRESS Serial No. Contract No. 17-235-13-25 08-0R5104 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 87% Location: Federal Project: 08-SBD-15-7.0/R20.0 STP-X071(67) STPH Progress payment No. 007 Payment period ending: 08-20-17 WESTCOAST PUBLIC WORK INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 682,731.90 13,050.00 2. a. Extra Work 80,000.00 80,000.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 762,731.90 93,050.00 5. Mobilization 80,000.00 0.00 6. Total Work Completed 842,731.90 7. Deductions -35,262.50 -35,262.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 807,469.40 57,787.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,787.50