Dept. of Trans. PROGRESS Serial No. Contract No. 14-113-16-42 08-0R6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 81% 08-RIV-10-R5.7/R53.1 Federal Project: NONE Progress payment No. 05 Payment period ending: 04-17-14 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 671,867.27 462,279.63 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 671,867.27 462,279.63 5. Mobilization 71,250.00 15,000.00 6. Total Work Completed 743,117.27 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -46,227.96 -46,227.96 c. Reduction after 95% Comp. 9. Total pay to Contractor 696,889.31 431,051.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 431,051.67