Dept. of Trans. PROGRESS Serial No. Contract No. 14-148-16-18 08-0R6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 97% 08-RIV-10-R5.7/R53.1 Federal Project: NONE Progress payment No. 06 Payment period ending: 05-21-14 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 827,037.87 155,170.60 2.a. Extra Work 72,564.44 72,564.44 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 899,602.31 227,735.04 5. Mobilization 75,000.00 3,750.00 6. Total Work Completed 974,602.31 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -69,001.46 -22,773.50 c. Reduction after 95% Comp. 9. Total pay to Contractor 905,600.85 208,711.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 208,711.54