Dept. of Trans. PROGRESS Serial No. Contract No. 14-267-14-28 08-0R6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 82% 08-SBD-15-31.8/171.4 Federal Project: NONE Progress payment No. 05 Payment period ending: 09-18-14 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 92711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 645,267.18 226,415.37 2.a. Extra Work 17,411.39 17,411.39 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 662,678.57 243,826.76 5. Mobilization 115,000.00 5,750.00 6. Total Work Completed 777,678.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -24,382.68 -24,382.68 c. Reduction after 95% Comp. 9. Total pay to Contractor 753,295.89 225,194.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 225,194.08