Dept. of Trans. PROGRESS Serial No. Contract No. 14-339-10-51 08-0R6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 100% 08-SBD-15-31.8/171.4 Federal Project: NONE Progress payment No. 08 Payment period ending: 11-18-14 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 92711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,123,009.23 42,559.35 2.a. Extra Work 21,267.45 0.00 b. Adjustment Comp. -21,750.00 -21,750.00 3. Materials on Hand 4. Earned Subject to Retention 1,122,526.68 20,809.35 5. Mobilization 115,000.00 0.00 6. Total Work Completed 1,237,526.68 7. Deductions -10,376.03 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,227,150.65 20,809.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,809.35