Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-009-11-12 08-0R6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-15-31.8/171.4 Federal Project: NONE Progress payment No. 09 Payment period ending: 12-09-14 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 92711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,134,523.23 11,514.00 2.a. Extra Work 36,303.32 15,035.87 b. Adjustment Comp. -21,750.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,149,076.55 26,549.87 5. Mobilization 115,000.00 0.00 6. Total Work Completed 1,264,076.55 7. Deductions -2,376.03 8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,261,700.52 34,549.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,549.87