Dept. of Trans. PROGRESS Serial No. Contract No. 18-128-13-41 08-0R7804 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 34% Location: Federal Project: 08-SBD-74-52.1/62.5 SSTG-P074(63) Progress payment No. 005 Payment period ending: 04-20-18 DREAMBUILDER CONSTRUCTION CORP 1324 LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 812,703.39 384,694.23 2. a. Extra Work 15,017.57 15,017.57 b. Adustment Comp. 3. Materials on Hand 555,855.07 -79,025.33 4. Earned Subject to Retention 1,383,576.03 320,686.47 5. Mobilization 366,937.50 0.00 6. Total Work Completed 1,194,658.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,750,513.53 320,686.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 320,686.47