Dept. of Trans. PROGRESS Serial No. Contract No. 13-266-16-59 08-0R8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 3% 08-SBD-38-51.9/ .0 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-17-13 MGP CONSTRUCTION P O BOX 355 UPLAND, CA 91785 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 224,351.89 224,351.89 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 224,351.89 224,351.89 5. Mobilization 6. Total Work Completed 224,351.89 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 224,351.89 224,351.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 224,351.89