Dept. of Trans. PROGRESS Serial No. Contract No. 16-266-10-55 08-0R9504 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 53% Location: Federal Project: 08-RIV-371-70.6/71.0 HSST-P P371-007(E) Progress payment No. 003 Payment period ending: 09-19-16 ALL AMERICAN ASPHALT 400 E 6TH ST CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 353,195.05 178,733.62 2. a. Extra Work 4,200.00 4,200.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 357,395.05 182,933.62 5. Mobilization 6. Total Work Completed 357,395.05 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 354,395.05 179,933.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179,933.62