Dept. of Trans. PROGRESS Serial No. Contract No. 24-205-10-14 08-0R9804 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 39% Location: Federal Project: 08-SBD-40-143.7 NONE Progress payment No. 002 Payment period ending: 07-20-24 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 475,884.00 377,508.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 475,884.00 377,508.00 5. Mobilization 6. Total Work Completed 475,884.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 475,884.00 377,508.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 377,508.00