Dept. of Trans. PROGRESS Serial No. Contract No. 24-354-12-19 08-0R9804 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 55% Location: Federal Project: 08-SBD-40-143.7 NONE Progress payment No. 004 Payment period ending: 12-20-24 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 579,964.00 104,080.00 2. a. Extra Work 19,739.19 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 599,703.19 104,080.00 5. Mobilization 6. Total Work Completed 599,703.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 599,703.19 104,080.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,080.00