Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 03-240-14-51 08-1A3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-RIV-60-15.8/15.9 Federal Project: NONE Progress payment No. 05 Payment period ending: 07-28-03 J MC LOUGHLIN ENGINEERING CO INC 10722 ARROW RTE STE 716 RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 189,889.20 0.00 2.a. Extra Work 595.44 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 190,484.64 0.00 5. Mobilization 20,000.00 0.00 6. Total Work Completed 210,484.64 7. Deductions 0.00 4,000.00 8. a.Contract Retentions -9,513.58 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9,513.58 0.00 9. Total pay to Contractor 210,484.64 4,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,000.00