Dept. of Trans. PROGRESS Serial No. Contract No. 04-056-15-58 08-1A7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 31% 08-SBD-15-8.8/10.2 Federal Project: NONE Progress payment No. 12 Payment period ending: 02-20-04 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 02078 Total Estimate This Estimate 1. Contract Itms Without Mobil. 62,273.43 4,418.58 2.a. Extra Work 7,910.12 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 70,183.55 4,418.58 5. Mobilization 6. Total Work Completed 70,183.55 7. Deductions 8. a.Contract Retentions -5,013.72 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 65,169.83 4,418.58 10. Reduction Amt to Escrow 11. Payment to Escrow 4,720.00 12. Net Pymt. this Estimate 4,418.58