Dept. of Trans. PROGRESS Serial No. Contract No. 07-085-08-57 08-1A9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 69% 08-SBD-15-74.1/86.4 Federal Project: NONE Progress payment No. 05 Payment period ending: 03-20-07 KIEWIT PACIFIC CO P O BOX 1769 VANCOUVER WA 98668 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,992,251.26 546,932.76 2.a. Extra Work 248,712.52 33,896.45 b. Adjustment Comp. 80,106.73 -537.27 3. Materials on Hand 4. Earned Subject to Retention 3,321,070.51 580,291.94 5. Mobilization 325,000.00 0.00 6. Total Work Completed 3,646,070.51 7. Deductions -500.00 0.00 8. a.Contract Retentions -166,053.53 -29,014.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,479,516.98 551,277.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 551,277.34