Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-334-09-58 08-1C0504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-79-R33.9/40.3 NHP-P079(37) Progress payment No. 008 Payment period ending: 06-16-16 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,244,137.23 0.00 2. a. Extra Work 16,320.81 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,260,458.04 0.00 5. Mobilization 48,000.00 0.00 6. Total Work Completed 1,308,458.04 7. Deductions 0.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,308,458.04 7,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,000.00