Dept. of Trans. PROGRESS Serial No. Contract No. 26-022-10-25 08-1C07U4 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 3% Location: Federal Project: 08-RIV-74-27.5/34.3 ACNH-P074(73) Progress payment No. 001 Payment period ending: 01-20-26 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 141,384.77 141,384.77 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 159,606.84 159,606.84 4. Earned Subject to Retention 300,991.61 300,991.61 5. Mobilization 6. Total Work Completed 141,384.77 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 300,991.61 300,991.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 300,991.61