Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 26-064-08-59 08-1C07U4 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 11% Location: Federal Project: 08-RIV-74-27.5/34.3 ACNH-P074(73) Progress payment No. 003 Payment period ending: 02-20-26 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 786,994.21 213,327.06 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 152,580.25 0.00 4. Earned Subject to Retention 939,574.46 213,327.06 5. Mobilization 455,500.00 0.00 6. Total Work Completed 1,242,494.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,395,074.46 213,327.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 213,327.06