Dept. of Trans. PROGRESS Serial No. Contract No. 26-082-07-49 08-1C07U4 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 18% Location: Federal Project: 08-RIV-74-27.5/34.3 ACNH-P074(73) Progress payment No. 004 Payment period ending: 03-20-26 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,002,453.47 1,215,459.26 2. a. Extra Work 19,922.72 19,922.72 b. Adustment Comp. 3. Materials on Hand 67,898.66 -84,681.59 4. Earned Subject to Retention 2,090,274.85 1,150,700.39 5. Mobilization 683,250.00 227,750.00 6. Total Work Completed 2,705,626.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,773,524.85 1,378,450.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,378,450.39