Dept. of Trans. PROGRESS Serial No. Contract No. 23-082-10-30 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 28% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 013 Payment period ending: 03-20-23 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,535,732.60 4,704,710.50 2. a. Extra Work 125,948.79 2,450.00 b. Adustment Comp. 3. Materials on Hand 6,207,712.21 -44,271.14 4. Earned Subject to Retention 36,869,393.60 4,662,889.36 5. Mobilization 17,921,750.00 3,773,000.00 6. Total Work Completed 48,583,431.39 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 54,791,143.60 8,435,889.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,435,889.36