Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-21-48 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 35% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 016 Payment period ending: 06-20-23 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,044,892.30 2,751,986.00 2. a. Extra Work 144,758.10 2,450.00 b. Adustment Comp. -16,603.38 -16,603.38 3. Materials on Hand 6,430,274.66 225,912.00 4. Earned Subject to Retention 44,603,321.68 2,963,744.62 5. Mobilization 17,921,750.00 0.00 6. Total Work Completed 56,094,797.02 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 62,523,071.68 2,961,744.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,961,744.62