Dept. of Trans. PROGRESS Serial No. Contract No. 23-205-18-54 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 38% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 017 Payment period ending: 07-20-23 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,075,731.00 3,030,838.70 2. a. Extra Work 172,433.35 27,675.25 b. Adustment Comp. -16,603.38 0.00 3. Materials on Hand 6,891,930.49 461,655.83 4. Earned Subject to Retention 48,123,491.46 3,520,169.78 5. Mobilization 17,921,750.00 0.00 6. Total Work Completed 59,153,310.97 7. Deductions -876,123.62 -874,123.62 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 65,169,117.84 2,646,046.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,646,046.16