Dept. of Trans. PROGRESS Serial No. Contract No. 23-259-13-19 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 43% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 019 Payment period ending: 09-20-23 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,290,641.50 4,379,471.10 2. a. Extra Work 182,113.21 0.00 b. Adustment Comp. -40,087.29 0.00 3. Materials on Hand 6,321,067.56 -255,947.33 4. Earned Subject to Retention 55,753,734.98 4,123,523.77 5. Mobilization 17,921,750.00 0.00 6. Total Work Completed 67,354,417.42 7. Deductions 0.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 73,675,484.98 4,126,523.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,126,523.77