Dept. of Trans. PROGRESS Serial No. Contract No. 23-296-08-50 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 46% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 020 Payment period ending: 10-20-23 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,612,965.20 8,322,323.70 2. a. Extra Work 202,109.77 19,996.56 b. Adustment Comp. -55,124.87 -15,037.58 3. Materials on Hand 6,181,898.68 -139,168.88 4. Earned Subject to Retention 63,941,848.78 8,188,113.80 5. Mobilization 17,921,750.00 0.00 6. Total Work Completed 75,681,700.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 81,863,598.78 8,188,113.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,188,113.80