Dept. of Trans. PROGRESS Serial No. Contract No. 23-325-01-40 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 48% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 021 Payment period ending: 11-20-23 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 63,778,222.30 6,165,257.10 2. a. Extra Work 262,510.50 60,400.73 b. Adustment Comp. -78,608.78 -23,483.91 3. Materials on Hand 5,631,625.44 -550,273.24 4. Earned Subject to Retention 69,593,749.46 5,651,900.68 5. Mobilization 17,921,750.00 0.00 6. Total Work Completed 81,883,874.02 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 87,513,499.46 5,649,900.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,649,900.68