Dept. of Trans. PROGRESS Serial No. Contract No. 24-052-09-56 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 55% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 024 Payment period ending: 02-20-24 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 79,376,907.60 5,842,082.10 2. a. Extra Work 354,164.37 59,662.08 b. Adustment Comp. -78,608.78 0.00 3. Materials on Hand 6,568,935.50 -380,551.56 4. Earned Subject to Retention 86,221,398.69 5,521,192.62 5. Mobilization 17,921,750.00 0.00 6. Total Work Completed 97,574,213.19 7. Deductions -21,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 104,122,148.69 5,520,192.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,520,192.62