Dept. of Trans. PROGRESS Serial No. Contract No. 24-082-11-55 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 57% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 025 Payment period ending: 03-20-24 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 84,608,546.90 5,231,639.30 2. a. Extra Work 355,914.37 1,750.00 b. Adustment Comp. -78,608.78 0.00 3. Materials on Hand 6,117,247.51 -451,687.99 4. Earned Subject to Retention 91,003,100.00 4,781,701.31 5. Mobilization 17,921,750.00 0.00 6. Total Work Completed 102,807,602.49 7. Deductions -20,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 108,904,850.00 4,782,701.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,782,701.31