Dept. of Trans. PROGRESS Serial No. Contract No. 24-145-09-19 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 62% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 027 Payment period ending: 05-20-24 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 94,362,916.40 4,557,539.40 2. a. Extra Work 365,382.03 9,467.66 b. Adustment Comp. -112,779.72 -1,902.38 3. Materials on Hand 5,417,391.79 -333,657.18 4. Earned Subject to Retention 100,032,910.50 4,231,447.50 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 113,480,518.71 7. Deductions -14,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 118,883,910.50 4,241,447.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,241,447.50