Dept. of Trans. PROGRESS Serial No. Contract No. 24-166-09-45 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 65% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 028 Payment period ending: 06-20-24 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,896,316.50 6,533,400.10 2. a. Extra Work 368,882.03 3,500.00 b. Adustment Comp. -112,779.72 0.00 3. Materials on Hand 4,551,308.51 -866,083.28 4. Earned Subject to Retention 105,703,727.32 5,670,816.82 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 120,017,418.81 7. Deductions -18,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 124,550,727.32 5,666,816.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,666,816.82