Dept. of Trans. PROGRESS Serial No. Contract No. 24-206-06-17 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 67% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 029 Payment period ending: 07-20-24 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,259,943.50 6,363,627.00 2. a. Extra Work 677,041.53 308,159.50 b. Adustment Comp. -112,779.72 0.00 3. Materials on Hand 4,292,558.15 -258,750.36 4. Earned Subject to Retention 112,116,763.46 6,413,036.14 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 126,689,205.31 7. Deductions -36,722.19 -18,722.19 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 130,945,041.27 6,394,313.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,394,313.95