Dept. of Trans. PROGRESS Serial No. Contract No. 24-327-08-21 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 78% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 033 Payment period ending: 11-20-24 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 132,793,638.70 2,368,414.90 2. a. Extra Work 1,361,516.88 12,182.89 b. Adustment Comp. -91,193.73 25,561.74 3. Materials on Hand 2,354,019.37 -249,066.78 4. Earned Subject to Retention 136,417,981.22 2,157,092.75 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 152,928,961.85 7. Deductions -31,722.19 8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 155,251,259.03 2,165,092.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,165,092.75