Dept. of Trans. PROGRESS Serial No. Contract No. 24-354-12-24 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 80% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 034 Payment period ending: 12-20-24 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 135,664,855.40 2,871,216.70 2. a. Extra Work 1,361,516.88 0.00 b. Adustment Comp. -91,193.73 0.00 3. Materials on Hand 2,622,220.85 268,201.48 4. Earned Subject to Retention 139,557,399.40 3,139,418.18 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 155,800,178.55 7. Deductions -31,722.19 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 158,390,677.21 3,139,418.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,139,418.18