Dept. of Trans. PROGRESS Serial No. Contract No. 25-111-10-34 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 89% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 038 Payment period ending: 04-20-25 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,459,417.00 7,027,973.60 2. a. Extra Work 2,674,720.43 853,664.05 b. Adustment Comp. -448,166.89 -427,973.16 3. Materials on Hand 988,513.44 -753,759.81 4. Earned Subject to Retention 159,674,483.98 6,699,904.68 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 177,550,970.54 7. Deductions -27,534.69 4,187.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 178,511,949.29 6,704,092.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,704,092.18