Dept. of Trans. PROGRESS Serial No. Contract No. 25-168-09-11 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 94% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 040 Payment period ending: 06-20-25 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 161,811,617.70 2,079,528.70 2. a. Extra Work 3,470,939.76 463,199.62 b. Adustment Comp. -448,166.89 0.00 3. Materials on Hand 534,583.99 -138,932.05 4. Earned Subject to Retention 165,368,974.56 2,403,796.27 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 183,699,390.57 7. Deductions -27,534.69 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 184,206,439.87 2,403,796.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,403,796.27